Thursday, August 27, 2009

Standing on the upstairs landing and looking up at ceiling joists and rafters. The roof is in pretty decent shape. However, the engineer will likely require that the valley rafters be beefed up like we were required to do at 403 N Queen.
The central upstairs bath only needs a bit of wall paper and paint and it will be ready to go.
Standing on east wall of parlor and looking west at fire place. The floor system has been removed. The floor you see is the dirt under the home. Flooring system on the entire first floor will need to be rebuilt. We will begin rebuilding this system as soon as we replace failed piers, band joist and central girder and after sealing the crawl space.