Wednesday, December 23, 2009
Randy, the greatest electrician in all of the world, wanted the portion of the southern wall, where the service head is to be located, painted ASAP. While Ahmad, the best painter I know, had his sprayer filled, he went ahead and primed all the siding that is currently up. Sherwin Williams tints primer so the blue we see is pretty close to the final shade. The gentleman in the photo is Adrian. He is a one of the best masons I know.
Friday, December 18, 2009
Wednesday, December 9, 2009
Thursday, November 26, 2009
Sunday, November 22, 2009
Monday, November 9, 2009
Here is the rig. A mixer dumps its load into the hopper of the pumper. The pumper pumps it through the 2-inch line to the men at the pour. The pump operator has a remote control that controls the flow. He stays with the concrete men and pumps when they call for more and turns it off when they say. Neat. Pumping two mixers full of concrete took about 3 hours. The pump operator said he could pump that amount in 30 minutes if they didn't need him to stop. Fun.
Since the site sits on top of hill, there is no way to get a concrete truck in there to pour. We had to hire a concrete pumper to pump all 17 yards of concrete up the hill. Due to the power lines, we could not hire a boom truck. And, since we needed to be able to move the nozzle around the pour, we hired a grout pumper with a 2-inch line. A 4-inch would be too heavy for the men to move around. In order to pump concrete through a 2-inch line, you have to get smaller aggregate. The smaller aggregate costs a bit more per yard.
Friday, October 30, 2009
Tuesday, October 27, 2009
Wednesday, October 14, 2009
Saturday, October 10, 2009
Wednesday, October 7, 2009
Wednesday, September 30, 2009
This is not an optical illusion. The 4x6 upright posts are plumb. At 8 feet above the top surface of the first floor, the house is leaning a full 5 inches. These uprights are braced to the new floor. We will use 2-ton winches to pull the house back into square. We are currently racking the southern and northern walls. In other words, we are making the west and east walls plumb. Once these two walls are plumb, we will rack the western wall (front of the house). We are also only doing one floor at a time. Once we have racked all four walls of the first floor, we will go upstairs and rack those walls. After each operation, we will be removing the siding and putting up 1/2 CDX Plywood (can't stand OSB) in order to hold the house upright. A builders wrap will be added prior to putting up the old siding. The old siding will likely be sanded, primed and painted off site. Then, the painters will put a final coat of paint on the siding after it is put back up.
Sunday, September 27, 2009
Thursday, September 24, 2009
Flooring system is shown in place under what will be the dining room. Flashing on wood is a termite shield. Flashing is galvanized steel. All joists are hung with Simpson Strong Tie hangers. Perimeter/Band Joist is comprised of three 2x10's. Central girder is also comprised of three 2x10's. Blocking is my preferred way of laterally bracing floor joists. Sub floor, where you see my compressor resting, is 3/4-inch CDX plywood. On top of CDX will be placed tar roofing paper and then old tough & groove flooring will be reinstalled.
Saturday, September 19, 2009
Friday, September 18, 2009
Inspector was out yesterday afternoon. All footing approved for pouring. Photos shows corner footing after concrete was poured. All footings have been poured as of Friday morning. 1st pier constructed today. Hope to have all piers constructed by the end of Monday and start putting in band joisting and girders.
Tuesday, September 15, 2009
The entire house is now sitting on blocks. Every pier under the house crumbled to the touch. All piers will be replaced. 20 footings have been dug and forms and steel are going in today and tomorrow. We should be calling for footer inspection by the end of this week. Hope to start pouring concrete by Friday.
Tuesday, September 8, 2009
Thursday, August 27, 2009
Standing on east wall of parlor and looking west at fire place. The floor system has been removed. The floor you see is the dirt under the home. Flooring system on the entire first floor will need to be rebuilt. We will begin rebuilding this system as soon as we replace failed piers, band joist and central girder and after sealing the crawl space.
Saturday, August 15, 2009
Wednesday, July 29, 2009
Friday, June 19, 2009
Subscribe to:
Posts (Atom)